Since our last construction update, the following milestones have been achieved on site:
Banksia Building
- Structure completed up to level 11.
- Windows have been installed up to level 7.
- Services rough-in and internal walls are complete to level 7.
Lacebark Building
- Structure completed up to level 12.
- Windows have been installed up to level 2.
- Services rough-in and internal walls are complete to level 7.
Enjoy the picture gallery below and see the buildings come to life.