Since our last construction update, the following milestones have been achieved on site:

Banksia Building

  • Structure completed up to level 11.
  • Windows have been installed up to level 7.
  • Services rough-in and internal walls are complete to level 7.

Lacebark Building

  • Structure completed up to level 12.
  • Windows have been installed up to level 2.
  • Services rough-in and internal walls are complete to level 7.

Enjoy the picture gallery below and see the buildings come to life.